Symptom
When running a job in app F2228 (Schedule Delivery Creation), the following error appears in the Job Log:
"An error occurred. Please create an incident on component LE-SHP-GF-JS."
In some cases, a related ABAP dump can also be found in the app "ABAP Runtime Errors" with the following detail:
"No more memory available to add rows to an internal table."
The job fails to create any Outbound Delivery and terminates without completing.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open app F2228 (Schedule Delivery Creation).
- Create or run an Application Job for Sales Order or Purchase Order processing.
- Set broad selection parameters - for example, no Distribution Channel, wide date range, or no Plant restriction.
- Run the job.
- Observe the error message in the Job Log. The Outbound Delivery creation fails.
Note: The issue may not reproduce in development or quality systems if those systems contain significantly fewer open Sales Orders or Purchase Orders than the productive system.
Cause
The Application Job attempts to process too many Sales Orders or Purchase Orders at once.
When the selection parameters are too broad (for example, no Distribution Channel or a very wide delivery creation date range), the system tries to create a large number of Outbound Deliveries in a single run. This exceeds the available memory and causes the job to abort.
This is why the same configuration can succeed in a DEV or QAS system, where data volume is lower, but fail in the productive system, where significantly more open Sales Orders or Purchase Orders are in scope.
Resolution
Narrow the selection parameters of the Application Job in app F2228 to reduce the number of Outbound Deliveries processed in a single run.
Recommended actions:
- Add a Distribution Channel to the job parameters to limit the scope of Sales Orders or Purchase Orders selected.
- Shorten the delivery creation date range (for example, use a rolling window of 30 to 60 days instead of PREVIOUSYEARUNTILTODAY).
- If the volume remains high, split the job into smaller batches - for example, by Plant, Sales Organization, or Sales Document Type.
- Run the updated job and verify that the Outbound Deliveries are created successfully.
Keywords
Application Job, Schedule Delivery Creation, Sales Order, Purchase Order, Outbound Delivery, Distribution Channel, LE-SHP-GF-JS, F2228, parameter selection, memory dump, ABAP Runtime Error , KBA , LE-SHP-GF-JS-2CL , Job Scheduling Apps Logistic Execution (Public Cloud) , LE-SHP-GF-JS , Job Scheduling Apps Logistic Execution , Problem