Symptom
You attempt to change the move-out date to the past with respect to the current move-out date, however on the C4C you are facing the error "Segment number 1: MR result does not meet Customizing requirements".
Environment
- SAP Cloud for Customer
- SAP Cloud for Customer Integration with SAP S/4HANA Utilities
Reproducing the Issue
- Go to the Utilities work center.
- Go to the Premises work view.
- Search and open the Premise ID 123456 (where 123456 means a generic Premise ID).
- Select the Customer under "Customer Overview".
- Click on "Change Move-Out".
- Change the "Move-Out" to a date in the past.
- Hit "Save".
Error: Segment number 1: MR result does not meet Customizing requirements.
Cause
There are missing SAP Notes which needs to be implemented and some settings in ISU.
Resolution
Firstly, please implement SAP Note:
2612225 - Upload error message without assignment to segment
2877935 - Redundant database access when uploading meter readings
Also, you need to customize the S/4HANA ISU for the changes of the meter reading results as move out data was changed following the steps below:
- Go to the SPRO - SAP Utilities.
- Go to the Device management.
- Select Meter Reading.
- Open Meter Reading result, select Change.
- Define Change process for reading data.
- There you need to maintain an entry with reading type and reading status requested from C4C.
Keywords
Segment Number 1; MR Result Does Not Meet Customizing Requirements; Change Move-Out Date; Segment; Number; MR Result; Customizing Requirements; Change; Move-Out; Date; C4C, Cloud for Customer, Utilities, Premises. , KBA , LOD-CRM-IND-UTL , Utilities , LOD-CRM-INT-S4H , Integration of C4C with S/4 HANA , LOD-CRM-INT-ERP , Integration of C4C with ERP , Problem