Symptom
In the Purchase Order Reminder Letter Runs, multiple proposals are being created for a single supplier instead of one proposal with all items.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Purchase Requests and Orders work center.
- Select the Purchase Order Reminder Letter Runs view.
- Observe that multiple proposals are created for the same supplier.
Cause
When there are over 200 objects (Purchase Orders), the system will split the proposals. This means that even Purchase Orders from one Supplier can be split into multiple proposals.
Resolution
System behavior.
Keywords
Purchase Order, Reminder Letter, Reminder Letter Runs , KBA , SRD-SRM-PRO , Purchase Requests and Orders , Problem
Product
SAP Business ByDesign all versions