3585104 - Planning calendar is not considered while calculating the delivery date in PR

Symptom

Material planning calendar has been maintained, but the delivery date cannot show according to planning calendar.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Set the Planning Calendar to material.
  2. Check its delivery date, it is not according to planning calendar.

Cause

Different MRP type is used instead of "Time-Phased Planning".

Resolution

To effectively control the delivery date, the MRP type should be set to "Time-Phased Planning".

See Also

Time-Phased Planning

Keywords

MRP, Planning, Planning Calendar, Calendar, Z04, MRP Type, Time-Phased Planning, R1, Public Cloud, Cloud, Controlled, PR, Purchase Requisition, Material, Planning Cycle , KBA , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions