Symptom
Material planning calendar has been maintained, but the delivery date cannot show according to planning calendar.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Set the Planning Calendar to material.
- Check its delivery date, it is not according to planning calendar.
Cause
Different MRP type is used instead of "Time-Phased Planning".
Resolution
To effectively control the delivery date, the MRP type should be set to "Time-Phased Planning".
See Also
Keywords
MRP, Planning, Planning Calendar, Calendar, Z04, MRP Type, Time-Phased Planning, R1, Public Cloud, Cloud, Controlled, PR, Purchase Requisition, Material, Planning Cycle , KBA , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions