Symptom
Inactive Material cannot be Removed from Purchasing Contract.
Environment
SAP Business ByDesign
Reproducing the Issue
- Work Center Sourcing and Contracting.
- Contract View.
- Search Contract ABC.
- Go to Item tab.
A Material 123 is inactive and you want to remove it, but it is not possible.
Cause
This is the expected system behaviour.
Resolution
When adding an inactive Material in a Purchasing Contract, the system will trigger a warning message telling you that this Material is inactive.
Once the Contract is Released, no Material can be removed.
Keywords
Purchasing Contract; Inactive Material , KBA , AP-PCP-PCT , Purchasing Contract , Problem