3586044 - Finish Good Receipt Date Misaligned with BOM Completion

Symptom

FG receipt date is not aligning with BOM completion because RM is received in the future, SFG is completed later, yet FG is scheduled earlier than its dependencies.

Environment

SAP S/4HANA Cloud Public Edition

Cause

System standard behavior

Resolution

MRP is not designed to align the FG receipt date dynamically based on component availability, and achieving this is not feasible. When MRP runs, it processes the BOM sequentially based on the low-level code, meaning the finished good (FG) is planned first, and a planned order is created.

Hence, when creating planned order for header material, the system does not know when the components will be available yet.

You can find more details in the 'See Also' section.

See Also

Factor sub-component manufacturing/supply times into MRP calculations

Keywords

MRP, SFG, Semi Finished Good, FG, Finished Good, Receipt, date, BOM, Misaligned, Completion Date, Public Cloud, Clou, Sub Components, Raw Materials, Planned , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem