Symptom
FG receipt date is not aligning with BOM completion because RM is received in the future, SFG is completed later, yet FG is scheduled earlier than its dependencies.
Environment
SAP S/4HANA Cloud Public Edition
Cause
System standard behavior
Resolution
MRP is not designed to align the FG receipt date dynamically based on component availability, and achieving this is not feasible. When MRP runs, it processes the BOM sequentially based on the low-level code, meaning the finished good (FG) is planned first, and a planned order is created.
Hence, when creating planned order for header material, the system does not know when the components will be available yet.
You can find more details in the 'See Also' section.