SAP Knowledge Base Article - Public

3588098 - Missing Fields in Project Data Sources for Planned Start and Finish Dates for Task

Symptom

The project related data Data Sources don't have the field "Planned Dates - Start Date" and "Planned Dates - Finish Date" for task.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Navigate to the available Data Sources for Projects.
  2. Attempt to locate the fields "Planned Dates - Start Date" and "Planned Dates - Finish Date".

Resolution

At present the data source for Projects does not include the fields "Planned Dates - Start Date" and "Planned Dates - Finish Date" for task.

As a workaround, use the following equivalences:

  • Planned Start date = Earliest Start date of the task
  • Planned End date = Latest Finish date of the task

Note: These dates will be accurate if the project was scheduled by the system. If there were any manual changes in the date and automatic scheduling was not done, these dates may differ.

See Also

Keywords

Project Data Sources; Planned Dates; Start Date; Finish Date;  , KBA , SRD-PRO-PMN , Project Management , Problem

Product

SAP Business ByDesign all versions