Symptom
The project related data Data Sources don't have the field "Planned Dates - Start Date" and "Planned Dates - Finish Date" for task.
Environment
SAP Business ByDesign
Reproducing the Issue
- Navigate to the available Data Sources for Projects.
- Attempt to locate the fields "Planned Dates - Start Date" and "Planned Dates - Finish Date".
Resolution
At present the data source for Projects does not include the fields "Planned Dates - Start Date" and "Planned Dates - Finish Date" for task.
As a workaround, use the following equivalences:
- Planned Start date = Earliest Start date of the task
- Planned End date = Latest Finish date of the task
Note: These dates will be accurate if the project was scheduled by the system. If there were any manual changes in the date and automatic scheduling was not done, these dates may differ.