3589124 - Unexpected Activity Value due to Small Quantities and Lot Size in Material Cost Estimate - SAP S/4HANA Cloud Public Edition

Symptom

For instance, in the Manage Cost Rates - Plan, below cost rate was created. 

Cost Rate=10000
Per=1
Activity Unit=HR

In the Material Cost Estimate, supposing the quantity is 0.004HR for 100 lot size, the activity value is 40. 

When modifying the lot size to 10 or 1, the activity’s unit of measure is converted to MIN or S, and the activity value is 10 (1/4 of the activity value with unit HR). 
This is not as expected. 


Read more...

Environment

SAP S/4HANA Cloud Public Edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem