3591042 - Need to run mrp sales order basis

Symptom

 Unable to run Material Requirements Planning (MRP) on a sales order basis.

Environment

SAP S/4HANA Cloud Public Edition

Cause

Standard system behavior

Resolution

In SAP S/4HANA Public cloud, it is not possible to run MRP on sales order basis because the multi-level, make-to-order (MTO) planning feature is no longer available. Instead, MRP runs are designed to be more streamlined and efficient, leveraging the speed of the HANA database.

Previously, this feature allowed planning for a selected planning segment rather than all segments, primarily as a performance optimization. However, with the enhanced processing capabilities of HANA, this additional complexity is no longer required, resulting in a simplified MRP process.

Moreover, the possible workaround for this is:
In the sales order item, you can set a Reason for Rejection (e.g., "Order cancelled due to error"), under the Sales A tab to temporarily block the requirement from MRP planning.

See Also

2268085 - S4TWL - MRP Live on SAP HANA - MD01N

Keywords

MRP, MRP Run, Sales order specific, Sales order, Schedule MRP Run, Sales order number, Cloud, Public cloud , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions