3594898 - Change of Resource Type in PPDS without Data Deletion Not Supported

Symptom

  • The need arises to change the resource type in PPDS from Single activity to Multi activity or vice versa.
  • This change cannot be made without deleting all orders/linked data on the resource, then deleting the resource and resending to PPDS.
  • The mentioned process is not feasible in a production environment.
  • Notes 629676 - Resource type conversion and 783068 were checked for compatibility but were found to be not applicable.


Read more...

Environment

Product Function: SAP S/4HANA > Manufacturing > Extended Production Planning and Scheduling > Production Planning and Detailed Scheduling

Product

SAP S/4HANA all versions ; SAP Supply Chain Management all versions

Keywords

PPDS, Resource Type, Single Activity, Multi Activity, Data Deletion, Technical Limits, SAP S/4HANA, Manufacturing, Production Planning, Detailed Scheduling, CR02, Workcenter, Capacity. , KBA , SCM-APO-INT-MD-RE , Resource , Problem