Symptom
In a Purchase Requisition (PR), when a contract is used as the source of supply, the system copies the "Planned Delivery Date" from the contract to the PR item.
However, the "Release Date" in the PR item is calculated incorrectly, as the system uses the Planned Delivery Time from the Material Master instead of using the Planned Delivery Time from the contract.
Read more...
Environment
- Materials Management (MM)
- SAP S/4HANA, version from 1709 to 2023
Product
Keywords
EEIND, BADAT, Purchase Requisition Release Date, FRGDT, Planned delivery time in days, PLIFZ, EBAN-EINDT, EBAN-PLIFZ, EBAN-FRGDT, LMEREQF15, l_frgdt_upd , KBA , MM-PUR-REQ , Purchase Requisitions , Problem