Symptom
Activity type and duration/work hours are added to maintenance order's operation, but planned cost of internal activity(YB1) is still 0.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create a maintenance order.
- Add the activity type and work/duration hours to the maintenance order's operation.
- Select Additional Functions -> Determine Costs.
- Select Costs tab, see planned cost of internal activity(YB1) is 0.
Cause
Ths issue is caused by missing/incorrect formula in work center, so the system cannot calculate the planned cost of activity.
Resolution
- Enter app "Change Work Center" and select Costing tab, assign Formula Key YBPM01 to work center. Formula Key YBPM01 is using Formula SAP_07(Work) which will take 'Work' during calculation;
- If need to calculate 'Duration', then Formula Key SAP004 which using Formula SAP_10(Duration) can be assigned to work center.
Keywords
Maintenance Order, Planned Cost, Cost Element, Value Category, YB1, Activity Type, Duration, Formula Key. , KBA , PM-WOC-MO-ACC-2CL , Controlling (budgeting, order costs) (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions
SAP Knowledge Base Article - Public