Symptom
When creating Material Cost Estimate (CK11N) error CK075 "Planning date is in the past -> cost estimate cannot be saved" is triggered.
Environment
SAP S/4HANA Cloud Public Edition
Cause
It is not possible to save a cost estimate with a date in the past, because the cost-estimate is only meant for the planning of a future price.
Resolution
If the system date is, for example, 01/01/2025, you should select a date after this to be valid.
Keywords
CK11N, cost estimation, planning date, CK 075, costing. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions