Symptom
You select a DateTime field in Integration Center, and would like to add/substract a value (e.g. switch to another time zone by adding hours).
Under "Edit Calculation", you try to configure but cannot adjust the time as you expect.
"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."
Environment
SAP SuccessFactors HCM
- Integration Center
Cause
Incorrect configuration
Resolution
Upper case letter is used here to specify the Unit of Time.
Please use "H" for hours, "D" for days, "W" for weeks, "M" for months, and "Y" for years.
e.g. "+ 8 H" for adding 8 hours to the field value
"+ 1 D" for adding 1 day to the field value
Keywords
IC job, Simple Calculated Field, Calculate, additional, amount, time unit, increase, decrease, time difference, data processing , KBA , LOD-SF-INT-INC-FWK , Integration Center UI Framework , Problem