Symptom
Schedule lines are being generated with bulk quantities instead of day-wise distribution after the MRP run. Although, PIRs are maintained day-wise, but the schedule lines are not aligning with this distribution.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Run the MRP
- Observe that the schedule lines are generated with bulk quantities instead of day-wise distribution.
Cause
The lot size procedure maintained in the material master is set to a value other than "Daily lot size (TB)".
Resolution
Maintain the lot size procedure as TB in the material master and run the MRP again and verify that the schedule lines are generated day-wise.
Keywords
MRP, Schedule lines, Bulk quantities, Day-wise distribution, SAP S/4HANA Cloud Public Edition, Material Requirements Planning, PIRs, Lot size procedure, TB. , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem