3604074 - Bulk Quantity Schedule Line generated Instead of day-wise distribution after MRP Run

Symptom

Schedule lines are being generated with bulk quantities instead of day-wise distribution after the MRP run. Although, PIRs are maintained day-wise, but the schedule lines are not aligning with this distribution.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Run the MRP
  2. Observe that the schedule lines are generated with bulk quantities instead of day-wise distribution.

Cause

The lot size procedure maintained in the material master is set to a value other than "Daily lot size (TB)".

Resolution

Maintain the lot size procedure as TB in the material master and run the MRP again and verify that the schedule lines are generated day-wise.

Keywords

MRP, Schedule lines, Bulk quantities, Day-wise distribution, SAP S/4HANA Cloud Public Edition, Material Requirements Planning, PIRs, Lot size procedure, TB. , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem