Symptom
A need to mark open purchase orders and scheduling agreements as delivery complete in mass in SAP S/4HANA Cloud Public Edition.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Navigate to the App Mass change to Purchase order.
- Proceed to Purchase order item.
- Select the Purchase orders.
- Click on mass edit.
- Look for the option to flag 'Delivery completed'.
Cause
Its a standard system behavior.
Resolution
- Go to the App Mass change to Purchase order.
- Navigate to Purchase order item.
- Select the Purchase orders.
- Click on mass edit.
- There is an option to flag 'Delivery completed'.
- Repeat the same steps for scheduling agreement in the app Mass change to scheduling Agreement.