3607791 - Investment Project settlement with additional sender line item

Symptom

When performing an investment project settlement to an Asset Under Construction (AuC), a separate sender line is generated with a cost element not maintained in the allocation structure.



Environment

SAP S/4HANA Cloud Public Edition

Cause

This issue occurs due to a vendor down payment posted to the project.

For more details, please refer to the SAP Help documentation:
Vendor Down Payment | SAP Help Portal

Note:

  • If the down payment is linked to a Purchase Order (PO), the cost element used will correspond to the one maintained under the Account Assignment tab in the Purchase Order.
  • If the down payment is not linked to a Purchase Order, the system will use the default General Ledger (G/L) account (e.g., 65001000).

Check below KBA for more details.

3545864 - Account 65001000 Doesn't Exist Error During Posting Down Payment Requests - SAP for Me

Resolution

As mentioned in the help document above:

You post the down payment to an investment project (WBS element) and settle it to an AuC. Before you can carry out a final settlement, you must have cleared the down payment with the invoice. You can then settle the AuC to the final asset.

Keywords

AUC, settlement, investment project, down payment, cost element, purchase order. , KBA , CO-OM-OPA-F-2CL , Period-end Closing (Public Cloud) , FI-FIO-AP-TRA-2CL , Transaction Apps: Public Cloud , FI-AA-AA-C-2CL , Transactions (Public Cloud) , Problem