Symptom
Commitments on cost center are updated even though the 'Lock Commitment Updates' indicator is enabled in the app 'Manage Cost Centers'
Environment
SAP S/4HANA CLoud Public Edition
Reproducing the Issue
- Activate cost center budgeting.
- Activate the "Lock Commitment Update" option in all cost centers.
- Observe that the system treats all cutover POs and PRs as commitment items and consumes the current year cost center budget.
Cause
Resolution
Currently on public cloud, the Lock Commitment Updates indicator doesn’t have any effect on the creation of commitment, it has only effect on the reporting. In detail:
The Lock Commitment Updates indicator in the relevant cost center master data is not selected if you want the commitments assigned to them to be included in your reporting.
See Also
Keywords
SAP S/4HANA Cloud Public Edition, Cost Center Budgeting, Lock Commitment Updates, Commitment Items, Purchase Orders, Budget Consumption. , KBA , CO-OM-CCA-AVC-2CL , Cost Center Budget Availability Control (Public Cloud) , FI-PRA-PRA-2CL , Process Simulation and Document Preparation (Public Cloud) , Problem