Symptom
When running MRP with Planning Mode '3' (Delete and Recreate Planning Data), the system does not delete existing planned orders or generate new ones, even though the mode is correctly selected. The MRP run completes without any changes or errors
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Run MRP with Planning mode 1 using "Schedule MRP Run" app.
- Go to MD04 and note the MRP element number.
- Run MRP for the same material with Planning mode 3 using "Schedule MRP Run" app.
- Check if the existing MRP element number is deleted and new number is created.
Cause
Planning Mode '3' (Delete and Recreate) only affects materials included in the MRP run. If there are no planning-relevant changes, the material is skipped, so existing MRP elements are not deleted or recreated.
Resolution
To ensure the system includes the material in the MRP run and reprocesses it fully, Planning Mode '3' should be used in combination with “Regenerative Planning”. This setting instructs the system to process all materials, regardless of whether changes have occurred.
See Also
Keywords
MRP run, Planning Mode 3, SAP S/4HANA Cloud Public Edition, Planned orders, Regenerative Planning, net change planning, Material Requirements Planning, Delete and Recreate planning data, Does not delete. , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem