3609859 - Planned Independent Requirement (PIR) type LSF is not reduced after Goods Issue with Movement Type 221 and Planning Strategy 10 Make to Stock Production

Symptom

During the Goods Issue of a reservation with movement type 221 the PIR of requirement type LSF is not reduced.
However, during the goods issue of a reservation with movement type 201, the PIR is reduced.


Read more...

Environment

  • SAP S/4HANA, on-premise Release Independent
  • SAP S/4HANA Cloud Private Edition Release Independent

Product

SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions

Keywords

planning strategy 10, make to stock production, make to stock, make-to-stock production, mts, strategy group 10, planned independent requirements, LSF, VSF, mov type 221, pir reduction, planned independent requirement reduction, PIR, Movement Type 221, Movement Type 201, Strategy 10, Reservation, Goods Issue, Requirement Type LSF, Requirement Type VSF, Strategy 40, MB21, MB26, ps_PSP_pnr, NPLNR, AUFNR, mseg, dependent reservation, Goods issue for a Project, project, wbs, wbs element, Goods issue for a Cost Center, cost center, migo, requirements_reduction, Abbautrategie , KBA , PP-MP-DEM , Demand Management , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.