3609908 - Tracking Budget Consumed Value in Project Budget Report - SAP S/4HANA Cloud Public Edition

Symptom

While the total budget figure is visible in the app "Project Budget Report - Overview(F3377)", it is not possible to track the budget consumed value and other budget related values, e.g. commitment, actual cost, assigned value, available budget, defined budget, etc. 

"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Navigates to Project Budget Report.
  2. While the total budget figure is visible, it is not possible to track the details. 

Cause

It is possible to track in the app "Project Budget Report - Line Items(F3378)". 

Resolution

  1. Select one or more projects or WBS elements.
  2. Choose View Details to navigate to view budget and costs at the line item level in the app "Project Budget Report - Line Items(F3378)". 

See Also

Project Budget Report | SAP Help Portal

Keywords

Project Budget Report - Overview, F3377, Project Budget Report – Line Items, F3378, Predictive Commitments, Project Budget Report , KBA , PS-COS-BUD , Budget , PPM-SCL-REP , Project Reporting (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions