Symptom
The system is not rounding off the values for Actual work and Overall outstanding work fields in project. The system is rounding off the values for Planned work as per the unit of measurement (UOM) configuration.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Project Management work center
- Select the Projects view and choose the relevant Project
- Go to the Project Plan tab and select the Work sub tab
- Enter the planned work. The system rounds off this value
- Observe that the Actual work and Overall outstanding work fields display the exact quantity without rounding off
Cause
The observed behavior is due to a new feature delivered in the 2502 version of the SAP Business ByDesign system. This feature applies the rounding off functionality based on the unit of measurement (UOM) configuration. However, this functionality is not applied to the Overall outstanding work field.
Resolution
In the what's new section for Project Management business area (Specific for 2502 version), there is a new feature.
Display the Decimals Based on UOM
The system adopts the decimal places for the project task service quantity value based on the unit of measurement specified in your Business Configuration settings.
This feature delivered in 2502 version of ByDesign.
https://help.sap.com/whats-new/2e5f185568e744db82065313bbbcc6ae?locale=en-US
In order to solve the rounding off issue, as a work around you can keep the zero decimals for the unit of measurement, so that no rounding will happen and system will show the actual values.
See Also
Refer to the "What's New" section for the project management business area for more information on the new feature related to the display of decimals based on UOM.
Keywords
Rounding off, Actual work, Overall outstanding work, Project UPG183, Unit of Measurement, UOM, Decimals, 2502 version. , KBA , SRD-PRO-PMN , Project Management , Problem
SAP Knowledge Base Article - Public