Symptom
- Repetitive manufacturing confirmation not possible due to missing plan calculation
- Error message RM175: "Existing standard cost estimate cannot be used"
Environment
SAP S/4HANA Cloud Public Edition
Cause
- The standard cost estimate does not have routing determined, which is required for backflush.
- The standard cost estimate was created before REM parameters enabled for the master material.
Resolution
- Create a new cost estimate for the master material for the new period.
- Release the new cost estimate.
- Perform backflushing with a date after the "costing date from".
See Also
Keywords
repetitive manufacturing, plan calculation, RM175, cost estimate, routing, backflush, sap s/4hana cloud, production version, special procurement type, subcontracting, MFBF, monthly closing , KBA , CO-PC-OBJ-2CL , Cost Object Controlling (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions