Symptom
Unable to select multiple products in preselected output products via ctrl+shift option during Mass Maintenance BOM run set up.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to work center Planning and Production Master Data.
- Access common task New Production Bill of Material Mass Maintenance Run.
- Select Add Input Product for BoM Mass Maintenance Options.
- Maintain all mandatory fields.
- Under Preselected Output Products.
- Add Row -> here select multiple products via value selection.
- Not able to select multiple products via Crtl+ Shift option.
Cause
Currently there is no option to select multiple output products via Ctrl+Shift in value selection under Preselected Output Products section.
Resolution
- Enter the output products of the BoMs that is to be updated via Add Row.
- If no output products are selected, all BoMs that contain the original input product gets considered for updating.