Symptom
When trying to consume a material in a Project Stock Order, this error pops up:
"Material not Available for Consumption in Project"
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project Management work center.
- Navigate to Project Stock Orders view.
- Find and select the relevant Project Stock Order ID.
- Choose Edit button.
- Select the relevant Line Item and click Consume.
- Enter the relevant Details and click OK.
- The system returns the error message: Material not available for consumption in project.
Cause
The field "Identified Stock Type" is empty in the Material Master Data.
Resolution
- Open the Material Master Data.
- Select the tab General and the sub-tab General.
- From here you will find the field "Identified Stock Type" being empty.
- Maintain an option such as "01- Batch" and Save.
Once this will be done, you should be able to consume your Material without error message.