Symptom
Need to know which value is considered as planned revenue for revenue recognition in app 'Plan Customer Project'.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The planned revenue can be shown under 'Work Package' tab and 'Billing' tab, sometimes, these 2 value can be different.
As mentioned in EBRR Cookbook, page 66:
On work package level, there is revenue calculated based on the planned resources. This plan revenue value is only for information and not relevant for revenue recognition.
On the Billing tab, the “amount to be billed” and billing plan must be maintained for the project. The value of “amount to be billed” can be different to plan revenue value calculated for all work packages. However, “Amount to be billed” is not taken as the basis for revenue recognition.
On the “Billing plan Definition” for a billing item, project manager can schedule individual billing due dates for this billing item. The total amount maintained in this schedule can be lower than the value of “Amount to be billed” but not higher. The planned revenue for revenue recognition is defined by the total amount maintained in the billing schedule.
Resolution
The planned revenue for revenue recognition is defined by the total amount maintained in the billing schedule.
See Also
Keywords
unexpected revenue, planned revenue, event-based revenue recognition, planned cost. , KBA , CO-PC-OBJ-EBR-2CL , Event-Based Revenue Recognition (Public Cloud) , Problem