SAP Knowledge Base Article - Public

3616873 - Commitment is not visible in the project budget report

Symptom

Commitment cost related to project stock not displayed in Project Budget report but displayed in the Project cost report app.

Environment

SAP S/4HANA Cloud Public Edition

Cause

Standard Behaviour.

Resolution

Commitment cost associated with the purchase of project stock through a purchase requisition or a purchase order is only relevant for Project Cost Report and will not be displayed in the app 'Project Budget Report'. 

See Also

Project Cost Report

Keywords

Commitment cost, project stock cost, account assignment type Q, project cost report, project budget report, SAP S/4HANA Cloud Public Edition, PPM-SCL-REP, , KBA , PPM-SCL-REP , Project Reporting (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions