Symptom
- Maintenance order operations with control key YBM1 are confirmed, and maintenance order is in CNF(Confirmed) status, after changing maintenance order status to OWMC(Main Work Completed), the maintenance order phase still remains in Execution. Expected phase should be Post Execution.
- At least one of maintenance order operations with control key YBM2 is not confirmed.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Edit maintenance order in app Change Maintenance Order.
- Operation with control key YBM2 not confirmed yet, there's at least one operation that has been final confirmed.
- Change system status to OWMC(Main Work Completed).
- Observe that the order phase still shows Execution, sub phase shows Main Work Started.
Cause
System expected behavior.
- This only happens when maintenance order contains more than one operations and as least one operation with control key YBM2.
- Operation with control key YBM2 not confirmed yet.
- As soon as at least one operation final confirmed, maintenance order gets status CNF(Confirmed).
- According to status profile settings, order phase will update to Post Execution and sub phase updated to Work Done only when status CNF(confirmed) is not set. So manually change order status to OWMC(Main Work Completed) cannot update order phase and sub phase.
Resolution
Complete confirmation or complete goods receipt for operations with control key YBM2. More details can be found in Help Documentation - Organizing External Maintenance Work
See Also
Keywords
Order phase, Execution, Post execution, Main Work Started, Main Work Completed, Confirmed, CNF, OWMC, maintenance order status, YBM2, YBM2. , KBA , PM-WOC-2CL , Maintenance Order Management (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions