Symptom
Some of the locations can be selected as ship-from location when creating new project stock order, however some of the locations are not there.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project Management work center.
- Select Projects view.
- Search for the Project ABC.
- Click Edit and navigate to Products tab.
- Select Products Overview under Products tab.
- Click on Create Project Stock Order button.
- Change the item type to pick-up and you are wondering how the ship-from location is proposed by the system.
Cause
System only proposes the location with logistics use - Moveable Storage
Moveable storage -- this usage captures mobile storages. This could be a truck or a van.
Note: For both project stock and movable storage, only one Logistics Area under a site can have these usages.
Resolution
- Go to Supply Chain Design Master Data work center.
- Go to Locations view.
- Select one of the sites and click Edit Layout.
- Add Child Logistics Area under the site and add logistics use Moveable Storage for the logistics area.
- Then the selected site will be shown in the ship-from location value help list for pick-up item type project stock orders.
Keywords
Project stock order, Ship-from location, Location, Moveable storage, logistics area, Pick-up , KBA , AP-PRO , Project Processing , Problem