Symptom
When a project is copied using app 'Project Control - Enterprise Projects', the Recognition Key is not copied/comes blank in the new instance.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create a new project using app Project Control - Enterprise Projects;
- Select the Project Profile as Project with Revenue.
- After confirming the creation, edit the project;
- Select the Billing Element flag and define a Recognition Key, under the Control section;
- Create a copy of the project generated in step 1;
- Notice that Recognition Key will not be copied/will be blank.
Cause
This is the expected system behavior.
When a project is copied, the Recognition Key field comes as blank per default.
Resolution
After confirming the copy operation for the new project, it is necessary to edit it and manually add the Recognition Key, by navigating to the Control section inside the project.
The same steps must be performed for relevant WBS Elements within the project, if necessary.
Keywords
S/4HANA Cloud, project, project control, enterprise project, new, copy, copied, key, recognition key, ra key, blank, empty, cleared, billing , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , Problem