Symptom

The data extraction time is happening too late/early to work with the data. Extraction should be outside the working hours. 

Environment

Settings for SAP Signavio Process Insights.

Cause

Random data extraction start times. 

Resolution

  1. the timing of the data extraction, when there are entries in the table /SDF/DCCLOGHDR, the data extraction will occur one week from that date and time, if the frequency is set to weekly.

    If you wish to schedule the data extraction to start at a specific time, please follow these steps:

    1. Stop the jobs related to the data collection.
    2. Delete the corresponding entries in the table /SDF/DCCLOGHDR.
    3. Start the data collection job at the time you want the data extraction to commence.

Keywords

data extraction, , set up time, sap signavio process insights, dcTimestamp, source data, configuration, delta filter, KFFI001201, process flows, performance indicators, data collection timestamp , KBA , BPI-SIG-PM-SET , Workspace Settings for SAP Signavio Process Manager , Problem

Product

SAP Signavio Process Manager all versions