Symptom
Is it possible to limit users on creating tasks using Cost center and activity type only? And how can this be achieved?
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to Manage My Timesheet.
- Click Manage my Tasks.
- Create Tasks.
Cause
How-To
Resolution
- Implement the BAdI HCM: Timesheet Validations (HCM_CATS_V1_TS_VALIDATION) to throw an error when a task other than WBS element or non project related task types are submitted.
- Refer to the following Community Link Restrict Tasks created in the Manage My Timesheet app.
See Also
Refer to: App Adaptability and Extensibility: Manage My Timesheet
Refer to: Restrict Tasks created in the Manage My Timesheet app
Refer to: KBA 0002973358 - SAP Community: Preferred Support Channel for How-To Questions
Keywords
limit tasks, cost center, activity type, manage my timesheet, sap s/4hana cloud public edition, BAdI HCM, HCM_CATS_V1_TS_VALIDATION, WBS element, non project related task types , KBA , CA-TS-S4 , Cross Application Timesheet in S/4HANA , How To