Symptom

Planned revenue is 0 for project with recognition key 'SPTMSR'.

Environment

SAP S/4HANA Cloud Public Edition

Cause

  • PRO03 is the correct planning category for revenue recognition key SPTMSR.
  • There are generally 3 planning categories for CPM:
  • PRO01 - Based on CPM baseline planning
  • PRO02 - Based on CPM Ongoing plan
  • PRO03 - CPM EAC (Estimation At Completion)

Resolution

To create the planned revenue for SPTMSR projects, ensure 'PRO03' is written via the "Transfer forecast to Finance job".

Keywords

EAC, inconsistent value, customer project, sap s/4hana cloud, revenue recognition, PRO03, planning category, accrual calculation, reporting, baseline, ongoing, estimation at completion, finance job , KBA , CO-PC-OBJ-EBR-2CL , Event-Based Revenue Recognition (Public Cloud) , Problem