Symptom
Planned revenue is 0 for project with recognition key 'SPTMSR'.
Environment
SAP S/4HANA Cloud Public Edition
Cause
- PRO03 is the correct planning category for revenue recognition key SPTMSR.
- There are generally 3 planning categories for CPM:
- PRO01 - Based on CPM baseline planning
- PRO02 - Based on CPM Ongoing plan
- PRO03 - CPM EAC (Estimation At Completion)
Resolution
To create the planned revenue for SPTMSR projects, ensure 'PRO03' is written via the "Transfer forecast to Finance job".
Keywords
EAC, inconsistent value, customer project, sap s/4hana cloud, revenue recognition, PRO03, planning category, accrual calculation, reporting, baseline, ongoing, estimation at completion, finance job , KBA , CO-PC-OBJ-EBR-2CL , Event-Based Revenue Recognition (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions
SAP Knowledge Base Article - Public