Symptom
The account assignment type in the purchase requisition generated through a material demand using the app 'Manage Project Demand' is not 'Q'.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create material demand using the Manage Project Demand app.
- Change the demand status to "Request to Save".
- Observe that the account assignment category "P" is populated in the Purchase Requisition (PR).
Resolution
The account assignment type in the purchase requisition is determined by the demand type.
- If the material demand type is 'Non stock material', then the account assignment type in the PR will be 'P'.
- If the material demand type is 'Project stock', then the account assignment type in the PR will be 'Q'.
Keywords
account assignment, purchase requisition, project demand, sap s/4hana cloud public edition, non stock material, project stock, manage project demand, demand status, request to save, PR, category P, category Q , KBA , PPM-SCL-DMN , Project Demand (Public Cloud) , PPM-SCL-DMN-FIO , Fiori UI for Project Demand (Public Cloud) , Problem