SAP Knowledge Base Article - Public

3634359 - No Supply Proposal Generated for a Product in a Planning Area After Planning Run

Symptom

There is positive net requirement quantity for product ABC in planning area DEF, it is expected that new supply proposal created after a planning run XYZ executed, but actually not.

*ABC represents product ID

*DEF represents planning area ID

*XYZ represents planning run ID

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning work center, access Products view.
  2. Search product ABC in planning area DEF, click Open.
  3. In the screen "Product Planning Details: ABC/DEF", net requirement quantity is greater than zero.
  4. Go to Supply Planning work center, access Planning Runs view.
  5. Select run XYZ, schedule a job immediately.
  6. Open the latest application log, select tab Results, no proposal created for product ABC in planning area DEF.

Cause

In the master data of Product ABC, under tab Planning, there is no planning group ID maintained for planning area DEF. However, planning run XYZ has specific scope of planning group maintained.

Resolution

In the master data of Product ABC, under tab Planning, maintain corresponding planning group ID for planning area DEF.

See Also

3557545 - Issue with Planning Run Considering Products with Excluded Planning Group ID https://me.sap.com/notes/3557545

Keywords

Planning Run, Supply Planning, Planning Group, MRP, Proposal , KBA , AP-SDM-MRP , Material Requirements Planning , Problem

Product

SAP Business ByDesign all versions