3635050 - Missing planned revenue error for WBS element level raised even when the plan data is imported to project

Symptom

Revenue recognition failed for project due to error message: 'Maintain plan revenues suitable for WBS element xxx using revenue method xx'.

Environment

SAP S/4HANA Cloud Public Edition

Cause

For RA key EPMFR, the cost is recognized based on the revenue-based percentage of completion (POC) method. Thus, the planned revenue is necessary, and the accrued cost is calculated based on the actual cost * actual revenue/planned revenue. Since there's no planned revenue, the error 'Maintain plan revenues suitable for WBS element xxx using revenue method xx' is raised and the revenue recognition is not triggered.

Resolution

Kindly make sure the planned revenue is imported using cost element category '11' or '12' and this account is assigned to a revenue recognition revenue source.
Besides, make sure the planned revenue is imported to WBS element level, the planned revenue imported to project level only(with empty WBS element) is not applied here.

See Also

Refer to: Posting Logic Revenue Recognition Key EPMFR

Refer to: SAP Note 0002838282

Keywords

revenue recognition, planned revenue, WBS element, POC method, event-based revenue recognition, error message, SAP S/4HANA Cloud Public Edition, financial plan data, real-time errors, manage real-time revenue recognition issues, EBRR. , KBA , CO-PC-OBJ-EBR-2CL , Event-Based Revenue Recognition (Public Cloud) , Problem