Symptom
The EAC (Estimate at Completion) values in the "Projects - Baseline/EAC/Ongoing" app are not consistent with the EAC values displayed in the "Review Customer Projects" app.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open the "Review Customer Projects" app.
- Check the EAC value for a specific project.
- Open the "Projects - Baseline/EAC/Ongoing" app.
- Compare the EAC value for the same project.
Cause
The "Projects - Baseline/EAC/Ongoing" app follows a different logic for EAC calculations. This discrepancy leads to differing EAC values. The app is planned to be deprecated in the future.
Resolution
- Use the "Projects – Plan/Actual" app (W0080) to review the EAC data for customer projects.
- In the "Projects – Plan/Actual" app, select the plan category CPM Projects EAC (PRO03) to view the correct EAC data.
- Schedule the job to transfer the estimate at completion via the "Transfer Project Forecast to Finance" app (F7292) to ensure the EAC data is updated in Finance.
See Also
Keywords
eac discrepancy, projects baseline/eac/ongoing, review customer projects, sap s/4hana cloud, estimate at completion, etc missing, plan/actual app, cpm projects eac, pro03, transfer project forecast to finance, sap knowledge base article. , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , CO-FIO-OM-IS-2CL , Reporting (Public Cloud) , Problem