3642870 - Requirement quantity changes after scrap confirmation in production orders.

Symptom

During a scrap confirmation, the requirement quantity of components may change:

Scenario A:

-The requirement quantities of components assigned to subsequent operations are reduced if the confirmed yield for the predecessor operation is less than planned. 

Scenario B:

-The requirement quantities of components assigned to subsequent operations are increased if the confirmed yield for the predecessor operation is less than planned.

Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA Cloud Private Edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions

Keywords

scrap confirmation, requirement quantity increase, production orders, operation quantity, CO11N, CO02, scheduling profile, quantity adjustment, recalculation logic, CO_MK_RESB_AMOUNT, CO_ZF_ORDER_ADJUST_AFTER_SCRAP,  requirement quantity decrease, OPKP, Adjust Quantities in Order to Actual Values. , KBA , PP-SFC-PLN-CPT , Components , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.