Symptom
- The requirement to adjust availability control (AVC) logic to check commitment budget availability at the contract level and payment budget availability at the purchase order (PO) level.
- Both contracts and POs are categorized as commitments, and there is no standard update profile to separate them into distinct ledgers.
- The update profile currently dictates the ledger updates per value type, which does not meet the described requirements.
Read more...
Environment
- Availability Control
Product
SAP ERP all versions ; SAP S/4HANA all versions
Keywords
availability control, avc logic, commitment budget, payment budget, update profile, sap s/4hana, public sector management, funds management, custom avc ledgers, contracts, purchase orders, earmarked funds, ledger separation, sap consulting, sap support. , KBA , PSM-FM-BCS-AC , Availability Control , PSM-FM-UP-CM , Commitments , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.