Symptom
Reorder pointing planning is used for the material. In the MRP type, it is configured that external requirements are included in the planning.
After running MRP for the material, there is not any procurement proposal created for the external requirement even if its requirement date is within the the replenishment lead time.
Read more...
Environment
SAP S/4HANA Cloud Public Edition
Product
Keywords
Scheduled MRP Run, purchase requisition, regenerative planning, planning file entries, reorder point planning, replenishment lead time, planning mode, MRP type, Monitor Material Coverage , KBA , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem