Symptom

End date does not replicate to the connected system for purchase requisitions in the 3EN scenario.

XML messages from the HUB system to the connected system do not capture the start date and end date correctly.

The Purchase Requisition in the connected system will be created with the wrong date. 


Read more...

Product

SAP Ariba Central Procurement 1.0 ; SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP S/4HANA 2023 ; SAP S/4HANA 2025 ; SAP S/4HANA for central procurement, integration with SAP ERP 1.0

Keywords

purchase requisition, PR replication, 3EN scenario, start date, end date, XML mapping, SAP S/4HANA, central procurement, service items, HUB system, connected system, mapping issue, 2025OP, CL_MMPUR_HUB_PR_REPLI_MAP_OUT, MAP_ITEM_ABAP2XML, missing dates , KBA , MM-PUR-HUB-PR , Processing Purchase Requisitions centrally , Problem