3644995 - Confirmed scrap quantity in the Order Headers list is shown as cumulative quantity of each operation in Monitor Production / Planned Orders app

Symptom

In Monitor Production / Planned Orders app Order Headers list, for confirmed scrap quantity, it’s shown as the cumulation of scrap quantity in each operation instead of the scrap quantity of the last operation, which is like the confirmed quantity.

Environment

SAP S/4HANA Cloud Public Edition 

Cause

It's standard system behavior that the calculation logics of confirmed scrap quantity and confirmed quantity are different at order header level.

For confirmed quantity, the system takes the quantity of the last operation directly. 
For confirmed scrap quantity, the system cumulates the scrap quantity of each operation. The reason is that a piece of material can only be scrapped once, so it's necessary to sum up all confirmed scrap quantities of each operation.

Resolution

If the requirement is to check the confirmed scrap quantity of each operation, go to Operations list in Monitor Production / Planned Orders app.

Keywords

order header, production operations, confirmation, scrap quantity, CO11N, Monitor Production / Planned Orders, COOIS , KBA , PP-SFC-EXE-CON-2CL , Confirmation (Public Cloud) , Problem