Symptom
The overhead calculation is executed via app 'Run Overhead Calculation - Actual' for project, however, there's no overhead cost shown.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The overhead setting is maintained per plant level, however, there's no 'Plant' maintained in the project master data.
Resolution
The 'Plant' field may not be shown when creating new project, kindly ensure both fields 'Plant' and 'Costing Sheet' exist in project master data.
And kindly edit the project master data and add the 'plant' manually and calculate the overhead again.
Keywords
Project, overhead calculation, costing sheet, overhead rate, KZS2. , KBA , CO-OM-2CL , Overhead Cost Controlling (Public Cloud) , Problem