Symptom
When changing the project currency during the creation of a new project using copy function in "Plan Customer Projects" app, the new project cannot be created because of message "The system is busy processing data."
Environment
SAP S/4HANA Public Cloud Edition
Reproducing the Issue
- Open the "Plan Customer Projects" app
- Select a project and click Copy
- Edit the relevant fields for the new project and change the project currency
- Save the project.
- Observe that the system displays the message "The system is busy processing data" and shows a "Page Unresponsive" screen
Cause
One possible cause is missing of type P (Cost Planning) currency exchange rates for the relevant currencies.
Resolution
In the "Currency Exchange Rates" app, maintain the currency exchange rates for the currencies and dates relevant to the project for rate type P (Cost Planning).
See Also
KBA 3037484 - In Plan Customer Projects app, error "Sorry, the plan data couldn't be saved due to errors." when setting Stage "In Execution"
Keywords
plan customer projects, currency, professional services projects, rate type P, currency exchange rates, page unresponsive, the system is busy processing data, copy, project , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem
SAP Knowledge Base Article - Public