Symptom
The error CK240 "Cost component split with value of zero" is triggered during cost estimate CK11N.
After checking and adjusting according to below KBA, the issue still persists.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The material has a very small price and the costing lot size is 1 in the master data, the quantity in the cost estimate is also 1. This may have chance to cause round off of the price.
Resolution
Adjust the costing lot size to a large number (such as 100), then execute the create material cost estimate again to see the result.
See Also
Keywords
ck240, 3438506, material cost estimate, ck11n, small price, costing lot size , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem