Symptom
When copying a project in the Project Control app, the error message FHC_RUNTIME109: "Copy failed. Date is out of the validity" is triggered.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Navigate to the Project Control - Enterprise Projects app.
- Attempt to copy a project.
Cause
The planned finish date of the original project being copied is 12/31/2050, and the factory calendar validity is limited to the year 2050.
Resolution
- Adjust the planned finish date of the original project to a year earlier, such as 2049, to avoid the error.
Keywords
project control, fhc_runtime109, copy failed, date validity, factory calendar, planned finish date, enterprise projects, sap s/4hana cloud, I_factorycalendar , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , Problem