Symptom
Need to know how total variance of manufacturing orders is calculated.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
As introduced in Event-Based Variances | SAP Help Portal, the total variance is the difference between the actual costs debited to the object and the credit from goods receipt.