Symptom
Different Purchase Order output channels are desired to have different dispatch times.
For example, the EDI output is desired to be generated immediately after PO creation and approval, while the Print output is intended to be triggered manually later.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
To differentiate dispatch times for different channels:
- Set the Dispatch time in the Output Type to "1 - Immediately".
- In the Channel settings, configure different Dispatch times for each channel. For instance:
- Set EDI to "1 - Immediately".
- Set Print to "2 - Scheduled".
For the Scheduled channel's output, manually execute it through the app 'Print Scheduled Purchase Order'.
See Also
KBA 3238393 - How to Set the Purchase Order output Status to "Complete"
Keywords
purchase order, output status, to be output, completed status, scheduled dispatch, print scheduled purchase order, sap s/4hana cloud, public edition, operational procurement, purchase order processing, dispatch type, edi output, output type configuration , KBA , MM-PUR-PO-2CL , Purchase Orders (Public Cloud) , Problem