Symptom
- Technical Error PRPO_CBPE 003; report an incident.
- Product ABCD in planning area YYYY planned with failures; save and check results of interactive planning log.
- Error for proposal 8: Calling production proposal.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Supply Planning Work Center
- Select Products view
- Enter Product ID ABCD and planning area YYYY
- Choose Open
- Choose the button Run Planning and select Multi-Level BOM, then choose OK.
- System displays the error: "Technical error PRPO_CBPE 003; report an incident."
Cause
- In Supply Chain Design Master Data work center, which you maintain the Country/Region of the Locations is not same in the Business Configuration work center Implementation Project view
- Working day calendar in Business Configuration work center is scoped only for A and B, preventing proposal creation for other site IDs.
Resolution
- Maintain Same country in both Business Configuration work center Implementation Project view and in Supply Chain Design Master Data work center Locations view
- Maintain a working day calendar for the required country in the Business Configuration work center. Alternatively, ensure all site IDs are associated with A or B to align with the existing scoped working day calendar.
See Also
- Refer to: SAP Knowledge Base Article KB0712254.
- Refer to: SAP Knowledge Base Article KB0905676.
Keywords
Technical Error PRPO_CBPE 003, Supply Planning error, working day calendar, Business configuration, Planning Area, multi-level BOM error, proposal creation failure, demand planning, MRP Run. , KBA , AP-DP , Demand Planning , Problem
Product
SAP Business ByDesign all versions
SAP Knowledge Base Article - Public