SAP Knowledge Base Article - Public

3662915 - Technical Error PRPO_CBPE 003 during Supply Planning Execution

Symptom

  • Technical Error PRPO_CBPE 003; report an incident.
  • Product ABCD in planning area YYYY planned with failures; save and check results of interactive planning log.
  • Error for proposal 8: Calling production proposal.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning Work Center
  2. Select Products view
  3. Enter Product ID ABCD and planning area YYYY
  4. Choose Open
  5. Choose the button Run Planning and select Multi-Level BOM, then choose OK.
  6. System displays the error: "Technical error PRPO_CBPE 003; report an incident."

Cause

  • In Supply Chain Design Master Data work center, which you maintain the Country/Region of the Locations is not same in the Business Configuration work center Implementation Project view 
  • Working day calendar in Business Configuration work center is scoped only for A and B, preventing proposal creation for other site IDs.

Resolution

  1. Maintain Same country in both Business Configuration work center Implementation Project view and in Supply Chain Design Master Data work center Locations view 
  2. Maintain a working day calendar for the required country in the Business Configuration work center. Alternatively, ensure all site IDs are associated with A or B to align with the existing scoped working day calendar.

See Also

Keywords

Technical Error PRPO_CBPE 003, Supply Planning error, working day calendar, Business configuration, Planning Area, multi-level BOM error, proposal creation failure, demand planning, MRP Run. , KBA , AP-DP , Demand Planning , Problem

Product

SAP Business ByDesign all versions