Symptom

When trying to change the cost center for a customer project in "Plan Customer Projects" app, notice that the cost center field is not editable.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Open "Plan Customer Projects" app and navigate to a specific project
  2. Click Edit and attempt to change the cost center for the project 
  3. Observe that the cost center field is not editable

Cause

Once a customer project has been saved, it is no longer possible to change the cost center for that project.

Resolution

Submit a feature request via the Customer Influence Portal.

See Also

KBA 2963059 - How to Submit Feature Requests for SAP S/4HANA Cloud Product